You may not know that removing a load-bearing wall without approved structural calculations can affect your building insurance and breach local regulations. Before you lift a tool, confirm the wall’s role, appoint a structural engineer, and secure the required building approval. You’ll also need temporary supports, correctly sized RSJs, and suitable padstones. Follow each stage carefully, because the most serious risks often arise before the wall appears to move.
Key Takeaways
- Confirm the wall’s load-bearing status by tracing loads through lofts, floors, basements, adjoining walls, and previous alterations.
- Hire a structural engineer to specify the RSJ, bearings, padstones, connections, temporary works, and required building approvals.
- Install engineered temporary supports with suitable spreader plates, inspect for hidden services, and monitor movement before removing masonry.
- Remove the wall progressively, prepare sound bearings, and install the RSJ level on approved padstones according to the engineer’s drawings.
- Obtain building-control inspection, complete specified fire protection, and retain certificates, photographs, calculations, and approval records before finishing.
Check If the Wall Is Load-Bearing

Before removing any wall, you must establish whether it supports loads from the roof, floors, or other structural elements.
Begin your wall assessment by inspecting the wall’s position, thickness, construction, and continuity through each storey. Check whether joists, rafters, beams, or walls above bear directly on it.
Examine the loft, basement, and adjoining rooms for evidence of transferred loads, altered openings, or previous work.
Don’t rely on appearance alone: lightweight partitions can conceal structural framing, while some masonry walls may be non-load-bearing.
A qualified professional should complete the structural analysis, particularly where load paths remain unclear or the building has unusual construction.
Keep photographs, measurements, and relevant property records.
Don’t remove finishes or expose structural components without appropriate precautions, and follow applicable building regulations and safety requirements throughout this investigation.
Arrange RSJ Calculations and Building Approval
Once you’ve confirmed the wall’s structural role, appoint a qualified structural engineer to calculate the required RSJ size, bearing lengths, padstones, connections, and temporary works. Their Structural engineering design should account for imposed loads, masonry condition, deflection limits, fire protection, and the building’s complete load path.
Request signed calculations and drawings, then submit them with your Building regulations application to your local authority or an approved inspector.
Don’t rely on online span tables or a contractor’s estimate: incorrect sizing can cause movement, cracking, or collapse.
Check whether planning permission, a party wall agreement, or additional consents apply, particularly in flats, listed buildings, or conservation areas.
Keep the approval documents on site, and confirm that the proposed materials and workmanship match the engineer’s specification before construction begins.
Support the Structure Before Removing the Wall
With the approved design and method statement in hand, install temporary works to carry every load above the wall before removing any masonry. Your competent contractor should position adjustable props, strongboys, needles, or a designed goalpost frame, based on the engineer’s calculations and site constraints.
Protect floors and ceilings with suitable spreader plates, and verify that the supporting structure can withstand concentrated loads. Check for hidden services, unstable masonry, and movement before loading the temporary system.
Your Structural assessment should confirm load paths, prop spacing, bearing lengths, and any required Foundation reinforcement. Keep access routes clear, restrict the work area, and prevent unauthorised entry.
Record inspections and monitor cracking or movement throughout the operation. Follow the approved method statement, Building Regulations, and health-and-safety requirements, stopping work immediately if conditions change.
Remove the Wall and Install the RSJ
After the temporary works have been inspected and approved, your contractor can remove the wall in controlled sections, starting at the top and working down without disturbing the props or adjacent masonry.
Your contractor must follow the engineer’s drawings, maintain safe exclusion zones, and remove debris progressively.
They’ll expose sound bearing points, prepare padstones to the specified dimensions, and check levels before lifting the RSJ into position with suitable, certified equipment.
The beam must achieve the required minimum bearings at each end and sit fully on the padstones.
Install any specified lateral restraint, pack gaps with approved materials, and prevent movement while the mortar cures.
Don’t alter the design on site.
If the opening affects wall aesthetics, discuss Decorative alternatives, such as boxed-in beams or matching finishes, only after structural installation is complete.
Complete Inspections, Fireproofing, and Finishing

Before closing up the work, have the building control officer inspect the completed installation against the engineer’s drawings, including beam size, bearings, padstones, restraint, and any required masonry repairs. Don’t conceal defects or proceed without approval. Confirm that your building permits and inspection records remain current, and obtain written sign-off where required.
Next, protect the RSJ against fire. Install the specified fire-resisting board system, encasement, or intumescent coating exactly as designed. Seal joints, service penetrations, and gaps to maintain the tested fire rating. Your fire safety measures must comply with the building regulations and the engineer’s or manufacturer’s details.
After approval and fireproofing, complete plasterboard, plaster, skirting, and finishes without damaging the protection. Keep photographs, certificates, product data, and completion documents. Retain them for future alterations, insurance, and property-sale enquiries.
Conclusion
By following each stage, you’ll protect your home, meet regulations, and achieve a sound result. Confirm the wall’s role, obtain engineered RSJ calculations, secure building approval, and install temporary supports. Remove masonry carefully, seat the beam on correctly specified padstones, and verify alignment. Then arrange inspection, apply approved fire protection, and complete finishes. Don’t rely on guesswork or shortcuts: plan thoroughly, support safely, build correctly, document everything, and keep certification for future records and compliance.